par energy_isere » 26 juil. 2025, 14:01
The first of four 520-tonne steam generators has been installed in the first unit of the Hinkley Point C nuclear power plant in the UK. 24 July 2025 WNN (Image: EDF) The carefully planned installation involved lifting the generator on to a special section of railtrack to be brought into the building. (Image: Screengrab from EDF/Youtube) It then had to be lifted and rotated into place where it will use the 295°C heat from the EPR reactor to turn water into steam to turn the turbine, to generate electricity. (Image: EDF) The installation brings an end to the journey for the 25-metre steam generator, which was manufactured by Framatome in France. The first of the eight steam generators that the two-unit plant will feature was delivered to the site in southwest England in May 2024 after a journey by sea and road. The first steam generator was delivered to the site last year (Image: EDF) Construction of the first of two 1630 MWe EPR reactors at Hinkley Point C began in December 2018, with construction of unit two beginning a year later. The dome of unit 1 was put in place in December 2023. The dome was lifted into place on the second unit's containment building last week. Last year, EDF announced that the "base case" was now for unit 1 being operational in 2030, with the cost revised from GBP26 billion (USD32.8 billion) to between GBP31-34 billion, in 2015 prices. When complete, the two EPR reactors will produce enough carbon-free electricity for six million homes, and are expected to operate for as long as 80 years.
par energy_isere » 19 juil. 2025, 11:19
Containment dome of Hinkley Point C unit 2 installed 17 July 2025 The dome of the containment building has been hoisted into place at the second unit of the Hinkley Point C nuclear power plant under construction in the UK. The milestone marks the end of the major civil engineering works on the plant's reactor buildings. Image: EDF Energy) Using one of the world's largest cranes, known as Big Carl, the dome - with a diameter of almost 47 metres, height of 14 metres and weighing 245 tonnes - was lifted and then slowly lowered onto the 44-metre-high reactor building. The dome is made up of 38 prefabricated panels which were shipped to Hinkley Point C and welded together in an onsite factory. Work will now begin to weld an air-tight seal around the joint between the dome and the reactor building, which will then be encased with 7000 tonnes of concrete. Construction of the first of two 1630 MWe EPR reactors at Hinkley Point C began in December 2018, with construction of unit two beginning a year later. The dome of unit 1 was put in place in December 2023. ................... .................
par energy_isere » 21 juin 2025, 00:26
Nucléaire: le fonds Apollo apporte 5 milliards d'euros au projet de Hinkley Point mené par EDF PL avec AFP 20 juin 2025 Le fonds américain Apollo va apporter un prêt de 4,5 milliards de livres (5,25 milliards d'euros), principalement pour financer le projet de réacteurs nucléaires de Hinkley Point C porté par EDF au Royaume-Uni, a annoncé vendredi le géant électricien français. Cet accord pour l'émission d'emprunts obligataires d'un montant maximum de 4,5 milliards de livres sterling, permettra "de sécuriser une part substantielle du financement en livres sterling de ses investissements au Royaume-Uni pendant les trois années à venir, en particulier le projet Hinkley Point C", a indiqué EDF dans un communiqué. ................ ................ EDF qui détient 72,6% dans le projet avait entrepris de rechercher des "partenaires" de financement pour ce projet alors que depuis 2023 son co-actionnaire à 27,4%, le partenaire chinois CGN a signifié qu'il n'entendait plus participer aux surcoûts supplémentaires. L'emprunt obligataire annoncé vendredi, remboursable au maximum dans 12 ans, pourra être utilisé "en trois tranches" dont la première "d'un montant nominal total de 1,5 milliard de livres sterling, sera émise le 26 juin", a précisé EDF dans un communiqué. EDF pourra ensuite utiliser les deux autres tranches en 2026 et en 2027.
par energy_isere » 04 avr. 2025, 15:15
Maxence Cordiez Ingénieur Il y a 3 semaines Aujourd'hui j'ai eu la chance de visiter le chantier des réacteurs nucléaires EPR d'Hinkley Point C au Royaume-Uni. Le chantier, qui fait intervenir 15 000 personnes, est particulièrement impressionnant (c'est très grand et de nombreux corps de métier interviennent en même temps). Une fois en service (en fin de décennie), les deux réacteurs produiront un total de 3,3 GW d'électricité bas carbone, c'est-à-dire environ la moitié de la puissance du parc nucléaire britannique actuel. Les EPR d'Hinkley Point devraient être suivis par ceux de Sizewell dans le Suffolk, copies conformes des premiers. Et parce que la visite d'un site industriel, aussi intéressante fût-elle, ne justifie pas à nos yeux l'empreinte carbone d'un vol en avion, avec Nicolas Goldberg nous y sommes allés en train via Londres. Un très grand merci à Simone Rossi et aux équipes d'EDF et EDF (UK) pour l'organisation de la visite et leur accueil sur place !
par energy_isere » 23 nov. 2024, 15:54
Generator stator arrives at Hinkley Point C 19 November 2024 The turbine generator stator for the Hinkley Point C nuclear power plant under construction in Somerset, England, has been delivered from the manufacturing plant in Belfort, France. The stator - measuring 12 metres in length and weighing 450 tonnes - was supplied by EDF subsidiary Arabelle Solutions. It was delivered to the construction site on 17 November following a journey via road, rail and sea. The stator is a key component of the turbine generator, serving as the stationary portion of an electric generator that converts the rotating magnetic field into electric current. EDF completed its acquisition of a portion of GE Vernova's nuclear conventional islands technology and services, including its Arabelle steam turbines, in May this year. The transaction included the manufacturing of conventional island equipment for new nuclear power plants as well as related maintenance and upgrade activities for existing nuclear plants outside of the Americas. EDF's acquisition of the business - at that time, known as GE Steam Power - was first announced in early 2022 and the final agreement was signed in the November of that year. Construction of Hinkley Point C - composed of two EPR pressurised water reactors of 1630 MWe each - began in December 2018, with unit 1 of the plant originally scheduled to start up by the end of 2025, before that was revised to 2027 in May 2022. In January, EDF announced that the "base case" was now for unit 1 being operational in 2030, with the cost revised from GBP26 billion (USD32.8 billion) to between GBP31-34 billion, in 2015 prices. When complete, the two EPR reactors will produce enough carbon-free electricity for six million homes, and are expected to operate for as long as 80 years. The stator arrives at the construction site (Image: EDF Energy)
par energy_isere » 26 oct. 2024, 12:19
In pictures: Hinkley Point C's second unit taking shape The third and top steel ring for Hinkley Point C unit 2's containment building has been lifted into place. Tuesday, 15 October 2024 The 423-tonne, 11.6-metre high and 47-metre diameter steel was lifted into place on Monday by the site's giant crane, called Big Carl. The steel ring is the final tier of the wall of the containment building, with its dome scheduled to be placed on top during 2025. The dome on the first unit was lifted into place in December and the first unit's reactor is set to be installed in the next few weeks. The steel structure will be encased in two layers of concrete to complete the containment wall of the reactor building. .........................
par energy_isere » 07 oct. 2024, 00:46
par energy_isere » 23 janv. 2024, 20:58
EDF : Au moins deux ans et £5 mds de plus pour les EPR d'Hinkley Point Le chantier des deux réacteurs nucléaires EPR de la centrale britannique d'Hinkley Point C accuse un nouveau retard d'au moins deux ans et un surcoût supplémentaire de 5 milliards de livres sterling au minimum (5,8 milliards d'euros) en raison de travaux de montage de tuyauteries et de câbles plus longs que prévu, a annoncé mardi EDF. REUTERS 23 janvier 2024 L'électricien public français, dont la filiale britannique EDF Energy construit le projet, a fait savoir dans un communiqué que son coût total, en valeurs 2015, était réévalué dans une fourchette comprise entre 31 et 34 milliards de livres, contre 25 à 26 milliards lors de la précédente revue, en mai 2022. Parallèlement, le début de la production d'électricité du réacteur n°1 d'Hinkley Point C (HPC) est désormais visé pour 2029, au lieu juin 2027 précédemment. EDF a cependant précisé que, dans son scénario le moins favorable, la facture pourrait encore augmenter d'un milliard de livres pour un démarrage de production qui n'aurait lieu qu'en 2031.
par supert » 19 déc. 2023, 15:22
par energy_isere » 18 déc. 2023, 21:34
supert a écrit : ↑18 déc. 2023, 16:12 46 GW de nuke pour charger des films de cul, transporter des parisiens en week-end et fabriquer des conneries de merde. Merci le nuke et EDF Supert qui a mis 100 000 watts dans l'or de ses cheveux
par supert » 18 déc. 2023, 16:12
par energy_isere » 17 déc. 2023, 20:18
mobar a écrit : ↑17 déc. 2023, 16:20 supert a écrit : ↑16 déc. 2023, 13:29 Ils ont montré leur incompétence, qui serait assez con pour encore les employer ? Les mêmes que ceux qui depuis plus de 40 ans nous enfument avec l'électricité la moins chère du monde, avec la soi-disant indépendance énergétique, la technologie d'avenir qui solutionnera tous les problèmes ... http://www.dissident-media.org/infonucl ... _disc.html Ce n'est pas un problème d'incompétence mais d'enfumage, le nuke est invendable, dangereux, ne sera jamais rentable et c'est la technologie la plus suicidaire dans un monde instable ou le terrorisme et la guerre peuvent s'inviter sans prévenir! Tous les acteurs le savent et pour le vendre raconter des salades à toujours été la règle!
supert a écrit : ↑16 déc. 2023, 13:29 Ils ont montré leur incompétence, qui serait assez con pour encore les employer ?
par mobar » 17 déc. 2023, 16:20
par supert » 16 déc. 2023, 13:29
par energy_isere » 16 déc. 2023, 11:33
Hinkley Point C landmark dome lift - in pictures 15 December 2023 Construction of the first EPR unit at the Hinkley Point C nuclear power plant in Somerset, UK, has reached a major milestone with the installation of the reactor building dome. The crane, known as Big Carl, is able to lift 5000 tonnes (Image: EDF YouTube live stream)